Traditional Culture Encyclopedia - Almanac inquiry - I don't know the process, how to decorate it?

Many friends are confused when pretending to install the steps for various reasons. You know, this will actually waste a lot of time and energy unco

I don't know the process, how to decorate it?

Many friends are confused when pretending to install the steps for various reasons. You know, this will actually waste a lot of time and energy unco

I don't know the process, how to decorate it?

Many friends are confused when pretending to install the steps for various reasons. You know, this will actually waste a lot of time and energy unconsciously.

Today I want to give you a smooth renovation process.

Before construction (about 3 days)

Determine the mode: install it yourself or find a designer? The final decoration design scheme, the specific budget of decoration construction and the construction party should be put in place;

Procedures: The procedures in different places will be a little different. If it is self-contained, it will be simpler. Basically, you only need to provide the owner's ID card, purchase contract, structural change diagram and sign various commitments. In addition, remember to pay all kinds of fees in time.

When a decoration company goes through the formalities, it must have the qualification, business license, identity and signature of the person in charge of the decoration in addition to the materials provided by itself;

Determine the start date: it is best to look through the almanac before starting work. Even if the family is not superstitious, it is always good to try to pay attention.

Protection of finished products: as long as they are not guerrillas, they will basically take protective measures for corridors, entrance doors, doors and windows at home to avoid accidental damage during decoration;

Disclosure and docking on the construction site: After the commencement date is determined, before the formal commencement, we will go to the site to dock with the designers and construction leaders, and communicate and determine the relevant requirements to avoid misunderstanding or rework in the later construction.

Officially started construction

After the structure is dismantled and modified, the dimensions of tiles, doors and cabinets can be measured. After that, all tiles, custom cabinets, cabinets and doors can be placed, and the quantity and delivery time can be determined.

Circuit modification (2~4 days)

According to the size of the apartment, determine the number of changes. Some only need local changes, and some have a heavy workload, which may require rewiring the whole room. There is only one master, and the construction period will be long;

Channel reconstruction (1~2 days)

When the circuit is reformed, the slotting part of the waterway reform will be completed together, so as long as the pipeline layout is carried out, it will not take too much time. If pre-water purifier, thermal cycle, bathroom wall-mounted washing machine and other equipment are added, the point of kitchen and bathroom waterway will be greatly changed, and the required time will be increased by 1~2 days;

Top equipment (5~8 days)

Central air conditioning: the installation will take about 3~5 days. Depending on the size of the apartment, if the apartment area exceeds1.30m2, the cycle may exceed 1 ~ 2 days. When setting up the equipment, remember to ask whether the package does not include the circuit part and whether you need the assistance of your own electrician;

Fresh air system: If the central air conditioner and fresh air system are bought by the same supplier, the installation speed may be relatively faster, which will reduce the connection time difference. The installation of fresh air pipeline is relatively simple, and the speed of fixed pipeline is faster than that of central air conditioning;

Waterproofing of balcony kitchen and bathroom (1 day)

The embedded toilet should be waterproof once before backfilling, do a closed water test after drying, backfill after drainage, and then make a waterproof layer after backfilling;

Woodworking approach (3~7 days)

The area of the ceiling is not only related to the size of the apartment, but also related to the determined design style. It usually takes 3~5 days to complete. If there is a multi-level ceiling or the work is complicated, the time will be extended.

Floor heating installation (2~4 days)

If you want to install floor heating, do it after installing the ceiling, so as not to accidentally hurt the water pipes of the floor heating when doing the ceiling. After two days of floor heating, you can start laying tiles;

Wall and ground reinforcement (1 day)

Wall fixing can enhance the adhesion of different materials before, but also effectively prevent dust, and it is not easy to loosen when sticking bricks. Generally, it is fixed after leveling or installing floor heating;

Masons enter the site (4~8 days)

If you plan to use wooden floors in your home except the kitchen, bathroom and balcony, it will be done soon; If the floor tiles of the whole room, or only the bedroom is wooden floor, there are patchwork or small horses, the progress will be slower; If it is an old house renovation, it will be waterproof and leveling again after demolition, and the construction period will naturally be longer;

After that, you can arrange the distribution of latex paint, the size of cabinets and wardrobes, and start production. You can also choose to customize the bathroom cabinet.

The painter enters the site (7~ 14 days)

There are about six processes in the simple wall technology, and in the process of leveling and putty, yin and yang angles should be added to protect the corner. There's no hurry here, wait until the wall is dry. Forced flushing may lead to later cracking, depending on the weather and actual situation.

After completing these, you can start purchasing sanitary ware, toilets, bathroom cabinets, cookers, range hoods, switch sockets and so on.

Wallpaper (2~3 days)

Families who want to paste wallpaper can apply basement membrane on the wall after spraying latex paint, and then paste wallpaper;

Installation of main materials (4~7 days)

Installation of all kinds of doors: after all doors are installed, they should be bricked and closed, and after all doors are installed, they should be closed and beautified with caulking agent;

Install the floor: Although the place where the wardrobe is customized may not be paved with wooden floors, it is best to install the floor first, and then install the wardrobe. If the skirting line of the wooden floor conflicts with the wardrobe, remember to close it after installing the wardrobe;

Install various cabinets: cabinets, wardrobes, bathroom cabinets, etc. , it can be installed normally;

Install sanitary ware: toilet or squatting pan;

Hardware installation: remember, the quality of hardware must be good;

Installation of ceiling: it is the ceiling of kitchen and bathroom;

Kitchen installation: range hood and cooker;

Install switch socket: try not to damage latex paint or wallpaper on the wall;

Electrical installation: kitchen and bathroom and household appliances.

Complete a project

Environmental protection detection: closed for 24 hours to detect formaldehyde, benzene, voc, etc.

Environmental protection management: problems should be dealt with in time.

Acceptance: check the quality, installation details and completion acceptance.

In this way, under normal circumstances, it only takes about 60~70 days of construction time to complete the installation of a flat house.

Ok, that's all for today.

Message: How big is your house? How long did it take to decorate?