How long does it usually take to decorate the villa?
The 300㎡ villa will be completed in about 9.7 months;
The construction period of 300㎡-500㎡ villa is about 1 1.5 months;
The construction period of 500㎡-800㎡ villa is about 13 months;
The construction period of villas over 800㎡ is about 14.5 months.
However, we should also consider the complexity of design and construction and the influence of various aspects.
Although the construction period is different in different areas of villa decoration, the whole process of villa decoration is the same. Take 300㎡ villa as an example:
1, design and contract signing takes about 30-60 days:
This stage depends on your own needs. The higher the general design requirements, the more detailed it is, and the longer the time, which generally takes 30-60 days, including floor plans, renderings, construction drawings, quotations and so on.
2. It will take about 45 days to dismantle and rebuild the structure:
Before renovation, the structure will be demolished and rebuilt according to the design scheme. If there is no such item, you can subtract this one.
3. Preparation for commencement is about 24 days;
The preparation stage is often ignored by many people, but it is actually very important. Because the preparatory stage of construction is completed, the quality, progress and control of subsequent construction can be guaranteed. During this period, a groundbreaking ceremony will be held, equipment and materials will be determined, and accurate pay-off will be carried out, generally about 24 days.
4, hydropower project about 36 days:
Water and electricity are the most important in the decoration process, which directly affects the comfort of life in the future. 300㎡ generally takes about 36 days, sometimes even longer.
5, mud wood engineering about 90 days:
The mud tile project includes waterproofing of kitchen and bathroom, tile laying and wall plastering. , and must pass the waterproof acceptance, generally about 90 days.
6, paint project about 45 days:
Painting projects include leveling and painting construction of walls, top surfaces, suspended ceilings and other foundations. The general working procedures are antirust treatment of base metal, flat binding treatment, base grid cloth treatment, gypsum square coating, putty leveling, primer 1 and topcoat twice.
7. The installation works will take about 120 days;
The final stage of installation includes customized material installation, various sanitary ware installation, floor installation and cabinet installation. If the products enter the site in time and the installation procedures are properly coordinated, the efficiency of installation and construction can be greatly improved to achieve timely delivery.
8. Completion stage:
In the completion stage, a comprehensive acceptance is required, such as whether the line connection is correct, whether the paint on the wall and top surface is uniform, whether the finish paint of wood products is in place, and the installation of sanitary ware and hardware.
After the acceptance, the decoration company will clear out and the owner can move in.
- Previous article:2020165438+1October 65438+Gregorian calendar year 04.
- Next article:How many kilometers is it from Ulan to Tongde?
- Related articles
- Zodiac auspicious day July 26, 2020 Gregorian calendar query
- Year of the tiger calendar. What year is the Year of the Tiger?
- Master, help me see what's wrong with the feng shui in this apartment.
- Gregorian calendar decoration began on an auspicious day. Inquiry 20 19
- In which dynasty did the Spring Festival originate?
- Is May 22nd, 2023 the best date for opening?
- Can you get married on the fifth day of the twelfth lunar month in 2022
- What should I pay attention to before and after moving?
- Inquiry about the opening date of the old yellow calendar
- Detailed wedding preparation strategies include wedding list and preparation items.