Traditional Culture Encyclopedia - Lucky day inquiry - Master who can use MPP, come in. It's engineering crossing diagram software.

Master who can use MPP, come in. It's engineering crossing diagram software.

You may not be very skilled in the control and use of calendars, so the suggestions are as follows:

1.6-28 to 7-22 is because the calendar you use is a "standard" calendar. "Standard Calendar" has 2 non-working days every week, so 7- 17 will not be "completion time".

2. There are many solutions, which are explained as follows:

A. Set a special working time for the task (that is, customize a special calendar for it, called the task calendar), as follows:

Step 1: Create a new base calendar.

(Menu) Tools-> Change working hours-> Create a new calendar-> (Enter a name and choose to copy the "Standard" calendar)-> Ok-> (For calendars, the newly created calendar name is displayed in the list box)->; Work week-> Details-> (Choose Sunday and Saturday)-> (Optional) Set the following specific working hours for the listed dates-> (Enter the time according to your working hours)-> (End)

Step 2: Apply a specific task to a specific calendar.

(Select your task) Right mouse button-> Task information-> Advanced-> (Calendar) Select the newly created calendar b.

B. use the resource calendar to control the schedule of tasks.

Tasks are completed by resources such as people or equipment. It will be more reasonable and useful if the working hours of these resources are set and the task schedule is arranged.

C. Adjusting the project calendar

When you think that the task of the project takes seven working days, please set the project calendar to seven working days. The modification method is similar to' 2'.

You usually use "resource calendar" to control the arrangement of tasks, and don't manually enter the completion date.

4. If you still don't understand, send the document to 4512 16782@qq.com and give it to you after adjustment.