(A) the main structure of the drilling rig
FYD-2200 split tower full hydraulic power head drilling rig consists of four independent parts: main engine, power station, drilling tower and mud pump. The outline and structural arrangement of the drilling rig are shown in Figure 2-6.
Figure 2-6 Outline and Structural Arrangement of Drilling Rig
1.
The main drilling rig consists of gripper, power head, chuck, power head frame, mast, upper section of mast, mast bracket, underframe, underframe assembly, main winch, hydraulic system, operating table and other parts. The main engine of drilling rig is shown in Figure 2-7.
2. Power plants
The structure of the power station is shown in Figure 2-8. Its function is to provide hydraulic power source for the main engine, which is connected with the main engine through the quick-change connector. The power station is mainly composed of power station frame 1, electric control cabinet 2, oil temperature radiator 3, oil pump motor set 4, oil tank 5, main pump 6, coupling 7 and main motor 8.
Figure 2-7 Schematic Diagram of Main Engine 2-7 FYD-2200 Drilling Rig
1- gripper; 2- Power head; 3- chuck; 4— Power head frame; 5- mast; 6-the upper part of the mast; 7— mast support; 8— bottom bracket; 9— underframe assembly; 10- main winch; 1 1- rope hoisting; 12- hydraulic system; 13- operation console; 14- power station
Figure 2-8 Physical Diagram of Power Station
1- power station framework; 2- Electrical control cabinet; 3- oil temperature radiator; 4— Oil pump motor set; 5— Fuel tank; 6— Main pump; 7- coupling; 8— Main motor
3. Operating table and field studio
The drilling rig operating system realizes the digital display of parameters such as speed, pressure, torque, pump pressure and flow rate, and realizes the video operation on the tower and the working state on site. The website is equipped with a remote network transmission system. Workstation and field studio are shown in Figure 2-9.
Step 4 equip
SG-24A four-corner drilling rig is adopted, with a bearing capacity of 550kN.
Figure 2-9 Operation Console and Field Studio
(a) the console; (b) On-site studio
5. Mud pump
Mud pump adopts BW300/ 12 type and is driven by split motor.
6. Rope coring winch
The rope coring winch is driven by split motor, and the fishing capacity reaches 3000 meters deep.
7. Drill pipe loosening system
Equipped with SQ 1 14/8 hydraulic power tongs.
(II) Main technical parameters of drilling rig
The main technical parameters of FYD-2200 split tower full hydraulic power head drilling rig are shown in Table 2-6.
(III) Application example of drilling rig
The Zhou Ji ZK 1725 hole in Huoqiu, Anhui Province used FYD-2200 split tower full hydraulic power head drilling rig for deep prospecting, with a depth of 2706.68m and a final aperture of Ф 77mm. In addition, in the NLSD- 1 hole construction of Duyunanling Scientific Drilling in Ganzhou, Jiangxi Province, a hole with a depth of 2967.83m and a final aperture of Ф 97mm was completed. The application shows that the rig has the following performance characteristics:
1) The drilling rig structure adopts split module design and the layout is reasonable. The whole drilling rig is divided into four independent parts: main engine, power station, drilling tower and mud pump, which is convenient for disassembly, relocation and transportation.
2) The heavy-duty 24m square pipe drilling rig can lift 18m stand, which saves 1/2 ~ 2/3 tripping time compared with mast drilling rigs that can only lift 9m and 6m stand.
3) The drilling process of the drilling rig is as long as 4.8m, which is suitable for wireline coring drill pipes and ordinary drill pipes with a length of 4.5m, saving drilling time. Compared with vertical drilling rig, the drilling time is 1/5 ~ 1/7 of vertical drilling rig.
4) The power head of the drilling rig can move the orifice longitudinally and transversely, and the orifice position is wide, which is convenient for tripping and coring operations.
5) The power head has a wide range of speed regulation, and the combination of mechanical gear shifting and hydraulic speed regulation can realize stepless speed change of 0 ~ 1200 r/min, and accurately control the speed of the power head.
6) The power head clamping system realizes the dual-purpose of chuck and top drive, and solves the problem that the chuck slips due to insufficient clamping force during shallow hole drilling with pressure and deep hole decompression.
7) The derrick can be added to the upper part of the slideway of the drilling rig, so that it can be used both with tower and without tower and with straight inclined hole.
8) The main drilling parameters are automatically collected and displayed on the operating platform, and the video images of the key operating parts above and below the tower body are displayed, so that the operation monitor can see the running state of the whole machine at a glance and enhance the safety of machine operation. At the same time, remote network transmission is realized, which is convenient for managers to make long-distance decision and command.
9) Equipped with hydraulic tongs to unscrew the drill pipe, which reduces the labor intensity of workers, reduces the damage of the drill pipe and saves the tripping time by about 1/3.
10) drilling rig, water pump, rope coring winch and other equipment are driven separately from the power station, which can save energy consumption of deep hole drilling by more than 20%.
Table 2-6 Table of Main Technical Parameters 2-6 FYD-2200 Full Hydraulic Power Head Drilling Machine
- Related articles
- A paper on rural development
- What are the advantages of Chinese medicine in treating tumors?
- A Case Study of American Pastoral Decoration
- Must-see scenic spots in Wuwei
- Yangxian county cultural art
- Simple style of American log bedroom
- Rhyming slogan of Dragon Boat Festival
- Foreigners who have created famous works like Hugo.
- How to write the ending of traditional culture in my eyes?
- How about Chuzhou ant moving co., ltd?