About the general method of project risk disposal, the following statement is incorrect ().

Answer: d

The risk-adjusted discount rate method uses a single discount rate to complete risk adjustment and time adjustment at the same time, which means that the risk increases with time, which may be inconsistent with the facts and exaggerate the risk of forward cash flow. So the statement of option d is incorrect.