Traditional Culture Encyclopedia - Traditional customs - Construction requirements of overhead power lines: cement pole method
Construction requirements of overhead power lines: cement pole method
Various vertical rod methods
Cement poles can be erected by truck crane, tripod, herringbone pole and pole (top fork). Construction personnel can choose the appropriate vertical pole method according to the actual situation.
Strict inclination requirements
There are strict requirements for the inclination of cement poles after erection. 10kV above the pole inclination should not exceed 3/1000 of the pole length; 10kV and below poles shall not exceed 1/2 of the top diameter of poles. This is the opposite of option BC.
Temporary stay wires control construction safety.
In order to ensure the safety of construction, temporary stay wires need to be set at the top to control and adjust the temporary stay wires evenly when poles are erected by pole-holding method and vertical rod method. At the same time, the vertical pole method is only applicable to vertical wooden poles and cement poles with a length less than 8m, which is different from option D..
- Previous article:What enterprises are there in Wenjiang?
- Next article:What does excellent style mean how to understand the meaning of excellent style
- Related articles
- What kind of service does the handling service belong to?
- Why is the yam powder in Zhang Baoshan so fragrant?
- Huawei TV set smart screen function introduction
- Rain flower stone, marble
- Xpeng Motors obtained the certification of UNR 155 vehicle network security management system. What will happen to its development?
- Classic public service poster-a public service advertisement poster offering love?
- How to make a dust-free workshop
- Revolutionary story of Jinggangshan
- What should I pay attention to when I teach myself English?
- How to play erhu smoothly?