Well-drilling contract

Well-drilling contract sample collection of 6

In the society where people pay more and more attention to the law, the use of the contract is more and more extensive, the signing of the contract is to protect the interests of both sides, to avoid unnecessary disputes. Then the format of the contract, have you mastered? The following is I help you to organize the well drilling contract 6, welcome to learn and reference, I hope to help you.

Well-drilling contract Part 1

Party A:

Party B:

Supervisory party:

According to the water conservancy construction investment plan and the needs of rural production and life, it is proposed that in

village of the new supporting machine wells 1 eye. In order to ensure the smooth implementation of the project, to ensure that the construction period and construction quality, by Party A, Party B and the supervisory party *** with the consultation, the formation of the following contract:

I. Project name:

Second, the project location:

Third, the construction of content:<

1, the use of drilling rigs to drill a new meter machine well, and is responsible for the well hole of the electrical survey work;

2, the installation of φ well wall pipe meters, filter water pipe meters and filter backfill;

3, supporting the installation of a type of submersible electric pump;

4, 3 × 4 meters well room a;

5, set up a low-voltage line meters.

Fourth, the contracting method and contract price:

The implementation of the lump-sum contracting method. The total contract price .

V. Responsibilities of the parties:

(a) Party A responsibilities:

1, the organization of townships and villages to determine the location of the wells and engineering and construction programs;

2, responsible for the supervision and inspection of the project and the coordination of work;

3, responsible for the organization of the project Acceptance of the work;

4, responsible for the allocation of state investment and self-financing management;

(B) Party B's responsibilities:

1, responsible for the mobilization of construction machinery, equipment and materials purchases and all construction work. Ensure that the construction content of the project is fully completed, quality and quantity, to meet the acceptance standards;

2, in accordance with the requirements of the relevant technical specifications for engineering construction, conscientiously do a good job of engineering construction, high standards to complete the construction task;

3, conscientiously abide by the provisions of the management of safety production, is responsible for all the safety of the construction site;

4, conscientiously do a good job of construction records, and timely analysis of the situation

(3) supervision party responsibilities:

1, responsible for the implementation of the well location, and provide the relevant electrical data and reference materials;

2, is responsible for doing a good job of the "three passes and one leveling", mud discharge and other construction environment coordination;

3, is responsible for the construction personnel, and the construction of a good job, and the construction of a good job, and the construction of a good job. p> 3, is responsible for the construction staff to provide food and lodging conditions, in the well pipe installation, packing to provide 10 of the labor force to work with;

4, is responsible for the quality of the construction site supervision and inspection;

5, is responsible for the implementation of self-financing million yuan.

Six, the quality of the project:

1, quality inspection and acceptance: Party A organizes the relevant departments to carry out inspection and acceptance;

2, the quality standard requirements: to achieve the qualified standard, and strive for excellent engineering;

3, the basis for acceptance: drilling project to the national acceptance specification of the drilling project based on the acceptance. To the well pipe smoothly into the well hole, pumps and equipment for safe operation, water output to meet the target as qualified; due to natural conditions caused by water quality, water quality problems, Party B is not responsible for; well-house based on the acceptance of construction engineering acceptance specification for the acceptance of the basis.

VII, project settlement and fund allocation

(a) Project Settlement: based on the budget program, combined with the actual completion of the situation and the contract settlement.

1, the difference between the actual drilling depth and the planned depth, the increase or decrease in cost per meter calculated in yuan;

2, the actual length of the well pipe and the difference between the plan, calculated in accordance with the budget unit price;

3, the total price of the contract for the construction of water supplied by the village group, the electricity is calculated in yuan per kilowatt-hour, the exceeding portion of the other calculations;

4, after the settlement of the project, the village group of the self-funding paid After the settlement of the project, the self-financing funds paid by the village group will be returned to the village group, and the shortfall will be quickly raised by the village group and handed over to the Party.

(2) funds disbursement:

1, self-financing by the beneficiary villages and groups to raise, hand over to the management of Party A, depending on the progress of the project to the B side of the phased disbursement;

2, the state investment: in accordance with the county treasury management approach to the disbursement of funds;

VIII, the construction period and the time frame

The total construction period is days. From the beneficiary villages and groups to pay the full amount of self-funding, within three days of the date of Party A issued a notice of commencement of work. Failure to complete on schedule, each extension of one day, deducted 2 ‰ of the total contract price of the project. Due to climate, geology and other special factors and in addition to Party B's own factors caused by the nest work, postponed on schedule.

IX, other outstanding matters can be agreed upon according to the construction situation.

X. This agreement in four copies. Party A, Party B, the supervisor of the party, from the self-financing in place after the effective.

Annex: List of total contract price

Party A: Representative:

Party B :: Representative:

Supervisor: Township Government Representative:

Village Committee Representative:

Month of the year

Drilling Contract Part 2

Party A (owner):

Party B (builder):

In accordance with the provisions of the Contract Law of the People's Republic of China *** and the State of China and the Regulations on the Management of the Construction Market of ____ Province, combined with the rules of trading of decorative works and the specific conditions of the project, the two sides in a friendly, friendly situation to reach the following agreement:

I. The main information of the contract:

Drilling works in the form of the form of the party to the Party B Construction.

2, the total cost of the project (capitals)

3, engineering information:

① Party A agreed to Party B to play the depth of the well for the time being set at meters, according to the drilling water sampling if the water samples do not meet the drinking water standards, agreed by Party A, Party B can increase the depth of the well.

② Tentatively set at 500 yuan per meter standard cost of drilling.

③ According to the location of the well determined by Party A, if Party B meets the gravel stratum caused by damage to Party B's drill bit, Party A will bear the cost of purchasing the drill bit.

4, project payment: 65% down payment on the day of signing the contract, yuan.

5, the construction period days, from ________ ____ month ____ day to ________ ____ month ____ day.

6, engineering warranty period ________ years.

7. The balance of payment will be settled within ____ days after the completion of the project.

8, according to Party A's request, Party B for Party A to bring a set of water extraction equipment, including deep water well pumps yuan, a set of well house, the amount of yuan, counted in the total amount of engineering contract calculation.

Party A to hand over their own located in the city road project over half of the mid-term payment of 30% yuan, the completion of the project to pay the balance of 5% a, amounting to yuan, a set of towerless water supply device, amount of

Party A (official seal): _________ Party B (official seal): _________

The legal representative (signature): _________ Legal representative (signature): _________

________ year ____ month ____ day ________ year ____ month ____ day

Well-drilling contract Part 3

Party A and Party B, after equal consultation, on Party A entrusted Party B to drill wells construction matters to reach the following terms:

First, the project location: next to the school gate room

Second, the construction period: construction period for the December 20, 20xx to December 25, 20xx, calendar days 5 days.

Third, the project and related requirements:

1, the construction project: a water well, into the actual depth of the well depending on the water table.

2, well pipe specifications: inner diameter 90cm, outer diameter 100cm, to ensure that the submersible pump and maintenance personnel up and down smooth.

3, well Fort requirements: must be strong, smooth surface.

4. water depth requirements: 60cm

Fourth, the project price:

1, drilling well depth of 6 meters or less 1800 yuan, such as more than 50 centimeters below the price of not charging another, () more than 50 centimeters according to the price of 300 yuan per meter manpower to pay the total price of the actual depth of drilling wells (under the tube meters) calculation shall prevail.

2, the total price of the project for Party A payable to Party B 's costs, including the cost of auxiliary materials, labor, transportation and miscellaneous costs, etc., in addition, Party A no longer pay any fees to Party B.

The total price of the project for Party A payable to Party B, including the cost of auxiliary materials, labor, transportation and miscellaneous costs.

Fifth, the payment method: the end of the project by the Party acceptance, Party A to pay 90% of the total price of Party B, reserved 10% of the total price as a quality assurance deposit, to be paid after one year.

Six, the obligations undertaken by Party A:

1, timely organization of the site required for construction.

2, to ensure that the construction of water and electricity supply, and bear the cost.

VII. Obligations undertaken by Party B:

1, responsible for the exploration work and drilling of wells required by the relevant facilities.

2, to ensure the safety of construction, such as violation of operating procedures and other reasons resulting in casualties and other accidents, Party B is fully responsible.

3, wash the well, dredging, to ensure that the depth of the well is not less than 7 meters. And assist the school will be dug out of the earth filled in the playground sand pit.

4, due to quality problems caused by the waste well, collapse, no water or water substandard, etc., by Party A to pay labor costs of 100 yuan per meter, but another site to play the well, the price of work with the previous, Party B is responsible for timely repair.

5, wells used one year (warranty period) within the quality and technical problems, Party B is responsible for maintenance, solution.

6, in addition to Party A should bear the obligations of the second paragraph, not included in this contract, the other matters of the project are Party B is responsible for.

Eight, this contract is not exhaustive, the two sides can sign a separate supplementary contract, and this contract has the same effect.

IX, this contract in duplicate, each party to sign a copy, effective from the date of signing.

Party A: Party B:

Date of signing of this contract: Monthly

In order to improve the quality of drilling wells, clear responsibilities, rights and benefits of both parties, to achieve the purpose of reciprocity, by the A and B agreed to the negotiation of the two sides, the establishment of the contract:

Party A: construction unit: Luzhou Tianyuan Packaging Products Co. Party B: Construction:

Legal representative:

I. Project Overview:

1, well location: Tianyuan plant

2, well structure: industrial water wells.

3, the depth of the water well: until the water source.

4, Requirements: After the formation of water wells using 8-centimeter water pipe for pumping, the adequacy of the water source must reach more than 24 hours, such as drilling wells do not come out of the water, the project losses borne by Party B itself.

Second, the project cost:

1, 10,000,000 rmb. (need to ensure that the water source is sufficient)

Third, Party A's responsibility:

1, unconditional provision of water and electricity used in the construction of Party B.

1, unconditional provision of water and electricity used in the construction of Party B.

4, Party B responsibility:

1, responsible for ensuring the quality of the project.

2, responsible for the well hole must use 160 pipe for construction.

3, responsible for equipment transportation, installation of wellhead.

4, safety responsibility: construction personnel, equipment, production safety are responsible for and undertake by Party B.

Fifth, bylaws:

1, this contract is signed by the representatives of the two sides, effective on the same day, with legal effect, drilling wells are completed, Party A to pay all the costs of the project after the abolition of their own.

2, this contract in duplicate, A and B each party to sign a copy of the other outstanding matters, the two sides to negotiate a solution.

Party A: Party B:

Representative: Representative:

Tel: ___________ Tel: ____________

Year month

Construction unit (Party A):

Construction unit (Party B):

Party A in order to solve the office and living water, the new one to play a 150 meters deep water well. Now entrusted to Party B construction. In order to ensure that the project is completed on time, quality and quantity, after full consultation between the two sides, the signing of this contract.

A project overview

1, project name: deep water well project

2, project location:

3, project content and scope of the contract: drilling, well pipe installation, gravel casting, sealing, cementing, pumping body installation, pumping, water, water, water temperature testing.

Second, the preparation before construction

1, before the construction of both sides to determine the location of the well.

2, Party B construction of electricity, water, mud discharge.

3, A and B **** the same agreed to June 30, 20xx started to July 2, 20xx completion.

4. Party B shall not subcontract or contract this project to a third party for construction.

3. Scope of works and standard of well completion

1. The well drilling works of this contract shall be contracted by Party B in the form of package contract, and the construction facilities, tools and personnel required for the works shall be completely borne by Party B. The well drilling works shall be carried out by Party B in the form of package contract, and Party B shall be responsible for the construction facilities, tools and personnel. Party B shall have the qualification conditions recognized for the construction works.

2. The works referred to in the contract are: drilling wells with aperture diameter ≧ 600mm, and using reinforced concrete welded pipe for the circle well pipe (length 4m×inner diameter 300mm).

3, into the well within three days after the A and B **** with the acceptance of the construction site, the verticality of the well hole in order to be able to successfully make the three-inch submersible pump head down to the bottom of the well shall prevail.

(1) Project price per meter unit price of 500 yuan. The latest well drilling contract model The latest well drilling contract model.

(2) Party B shall charge according to the drilling footage and the actual depth of the well, to be paid after acceptance after Party B invoice 10 days.

(3) The cost of water, electricity and oil consuming consumables for well drilling shall be borne by Party B.

We are not responsible for the cost of water, electricity and oil consuming consumables for well drilling.

Fourth, into the well acceptance

1, section acceptance (including the well depth, diameter of the cloth tube, filler material). A and B and the relevant departments signed as the basis for acceptance.

2, drilling depth to measure the depth of acceptance recognized as the basis for settlement of accounts.

V. Other Matters

1. Party B shall ensure that the water output of the well reaches ≧10-15 tons per hour, and if the water output is less than 10 tons per hour, Party A shall pay 50% of the cost of a single well project.

2. During the construction period, Party B should pay attention to the safety of construction, if there are casualties, Party B should bear all the costs of casualties.

3. After Party B transported the well-drilling equipment to the construction site, the construction period can be postponed due to power outage and force majeure circumstances encountered by human factors.

4. Other matters shall be resolved by mutual agreement, without affecting the construction period.

This contract is in four copies, each side of the two copies, the contract signed by both sides since the seal to take effect

Party A (official seal): Party B (official seal):

Legal representative: Legal representative:

Authorized person: Authorized person:

Date of signing:** month

Well drilling contract Part 4

The construction unit (Party A).

Construction unit (Party B):

Party A for the solution of office and living water, a new well about 150 meters deep. Now entrusted to Party B construction. In order to ensure that the project is completed on time, quality and quantity, the two sides fully negotiated, signed this contract.

Article I Project Overview

1, Project Name: Deep Water Well Project

2, Project Location:

3, Project Content and Scope of the Contract: Drilling, well pipe installation, gravel casting, sealing, cementing, pump installation, pumping, water, water temperature testing.

Second, the preparation before construction

1, before the construction of both sides to determine the location of the well.

2, Party B construction of electricity, water, mud discharge.

3, A and B **** the same agreed to June 30, 20xx started to July 2, 20xx completion.

4. Party B shall not subcontract or contract this project to a third party for construction.

3. Scope of works and standard of well completion

1. The well drilling works of this contract shall be contracted by Party B in the form of package contract, and the construction facilities, tools and personnel required for the works shall be entirely borne by Party B. The construction facilities, tools and personnel required for the works shall be fully covered by Party B. The well drilling works of this contract shall be carried out by Party B in the form of package contract. Party B shall have the qualification conditions recognized for the construction works.

2. The works referred to in the contract are: drilling wells with aperture diameter ≧ 600mm, and using reinforced concrete welded pipe for the circle well pipe (length 4m×inner diameter 300mm).

3, into the well within three days after the A and B **** with the acceptance of the construction site, the verticality of the well hole in order to be able to successfully make the three-inch submersible pump head down to the bottom of the well shall prevail.

(1) Project price per meter unit price of 500 yuan. The latest well drilling contract model The latest well drilling contract model.

(2) Party B shall charge according to the drilling footage and the actual depth of the well, to be paid after acceptance after Party B invoice 10 days.

(3) The cost of water, electricity and oil consuming consumables for well drilling shall be borne by Party B.

We are not responsible for the cost of water, electricity and oil consuming consumables for well drilling.

Fourth, into the well acceptance

1, section acceptance (including the well depth, diameter of the cloth tube, filler material). A and B and the relevant departments to sign as the basis for acceptance.

2, drilling depth to measure the depth of acceptance recognized as the basis for settlement of accounts.

V. Other Matters

1. Party B shall ensure that the water output of the well reaches ≧10-15 tons per hour, and if the water output is less than 10 tons per hour, Party A shall pay 50% of the cost of a single well project.

2. During the construction period, Party B should pay attention to the safety of construction, if there are casualties, Party B should bear all the costs of casualties.

3. After Party B transported the well-drilling equipment to the construction site, the construction period can be postponed due to power outage and force majeure circumstances encountered by human factors.

4. Other matters shall be resolved by mutual agreement, without affecting the construction period.

This contract is in four copies, each side of the two copies, the contract from both sides signed and sealed to take effect

Party A (official seal): Party B (official seal):

Legal representative: Legal representative:

Authorized representative: Authorized representative:

Date of signing:** month

A and B through equal consultation, on the party A Commissioned by Party B well construction reached the following terms:

First, the project location: next to the school gate room

Second, the duration of the requirements: the construction period for the construction of the December 20, 20xx to December 25, 20xx, the number of calendar days 5 days.

Third, the project and related requirements:

1, the construction project: a water well, into the actual depth of the well depending on the water table.

2, well pipe specifications: inner diameter 90cm, outer diameter 100cm, to ensure that the submersible pump and maintenance personnel up and down smooth.

3, well Fort requirements: must be strong, smooth surface.

4. water depth requirements: 60cm

Fourth, the project price:

1, drilling depth of 6 meters within 1800 yuan, such as more than 50 centimeters below the price of work, () more than 50 centimeters according to the price of 300 yuan per meter manpower to pay the total price of the actual depth of drilling wells (under the tube meters) calculation shall prevail.

2, the total price of the project is the cost payable by Party A to Party B, including the cost of auxiliary materials, labor costs, transportation and miscellaneous costs, etc. In addition, Party A will not pay any more to Party B.

Fifth, the payment method: the end of the project by the Party acceptance, Party A to pay 90% of the total price of Party B, reserved 10% of the total price as a quality assurance deposit, to be paid after one year.

Six, the obligations undertaken by Party A:

1, timely organization of the site required for construction.

2, to ensure that the construction of water and electricity supply, and bear the cost.

VII. Obligations undertaken by Party B:

1, responsible for the exploration work and drilling of wells required by the relevant facilities.

2, to ensure the safety of construction, such as violation of operating procedures and other reasons resulting in casualties and other accidents, Party B is fully responsible.

3, wash the well, dredging, to ensure that the depth of the well is not less than 7 meters. And assist the school will be dug out of the earth filled in the playground sand pit.

4, due to quality problems caused by the waste well, collapse, no water or water substandard, etc., by Party A to pay labor costs of 100 yuan per meter, but another site to play the well, the price of work with the previous, Party B is responsible for timely repair.

5, wells used one year (warranty period) within the quality and technical problems, Party B is responsible for maintenance, solution.

6, in addition to Party A should bear the obligations of the second paragraph, not included in this contract, the other matters of the project are Party B is responsible for.

Eight, this contract is not exhaustive, the two sides can sign a separate supplementary contract, and this contract has the same effect.

IX, this contract in duplicate, each party to sign a copy, effective from the date of signing.

Party A: Party B:

Date of signing of this contract: January

Party A:

Party B:** Limited Company After friendly consultation between Party A and Party B, now contracted by Party B to Party A belongs to the four metallurgical district of the roof, the outer wall and expansion joints of the waterproofing repair works reached the following agreement:

First, the project specific scope: Four metallurgical six part of the wall, roof leakage, expansion joints.

Second, the unit price: expansion joints according to the waterproof long time work quality maintenance terms for construction, unit price 560 yuan / m, quality warranty for twenty years. Ordinary expansion joints 230 yuan / m, quality warranty for three years. Polyurethane grouting according to the market price of leakage repair, the price of each household respectively between 700 and 900 yuan. Waterproofing of external walls at market prices per square 46 yuan, quality warranty for five years.

Third, the mode of payment: after acceptance by both sides, there is no leakage, Party A paid a lump sum to Party B project.

Fourth, Party B's responsibility: Party B into the construction site, to do with the customer communication relationship between the community, can not happen fights, brawls, riots, such as the occurrence of this phenomenon, Party A has the right to terminate the contract.

V. Safety and responsibility: Party B shall not drink, wear slippers during the construction period, the construction time is 30 days, without delay. Constructed places should be kept clean, neat, and keep the leadership of the property company with a good account of construction and maintenance in accordance with Party A's program.

Sixth, Party B in the construction period, such as the occurrence of all security accidents, all the responsibility for Party B, Party A does not bear any responsibility.

This agreement is in duplicate, after signing that will come into effect, if there are no matters to be negotiated between the two sides to make a supplemental agreement, Party A and Party B have the same legal effect.

Signature of Party A (seal):

Signature of Party B (seal):

August 26, 20___

Well Drilling Contract Part 5

Party A:

Party B:

Party A and Party B, after equal consultation, Party A entrusted Party B with the construction of a well to agree on the following terms:

One, Project location: xx city, xx province

Second, the duration of the requirements: construction period for the month of 20xx to 20xx, calendar days days.

Third, the project and related requirements:

1, the construction project: a water well, into the well actually down the tube meters not less than 150 meters.

2, well pipe specifications: internal diameter 286mm, external diameter 350mm, length 8000mm, to ensure that the submersible pump up and down smoothly.

3, the choice of materials: pipe for the cement welded pipe, the filter material must be sifted rice stone, and mixed with coarse sand.

4, well Fort requirements: must be achieved solid, smooth surface.

5, technical requirements: to ensure that the water output, sand content, etc. in line with the national "Well Construction Code" standards.

Fourth, the price of the project:

1, drilling wells per meter unit price of yuan, the total price to the actual drilling depth (under the tube meters) calculation shall prevail.

2. The unit price and total price is the cost payable by Party A to Party B, including the cost of the main materials of the cement pipe, auxiliary materials, labor, transportation and miscellaneous costs, taxes and other costs, in addition, Party A will not pay any more to Party B.

We will not pay for the cement pipe to be drilled, but we will pay for the cement pipe to be drilled.

Fifth, the payment method: the end of the project by the Party acceptance, Party A to pay 90% of the total price of Party B, reserved 10% of the total price as a quality assurance deposit, to be paid off after one year.

Six, Party A's obligations:

1, timely organization of the construction of the required site, dug a good cistern.

2, to ensure that the construction of water and electricity supply, and bear the cost.

7, Party B's obligations :

1, in accordance with the national "well construction specification" organization and construction, is responsible for the exploration work and drilling of wells required for the relevant facilities.

2, to ensure the safety of construction, such as violation of operating procedures and other reasons for casualties and other accidents, Party B is fully responsible.

3. After washing and desilting the well, the depth of the well is guaranteed to be not less than 150 meters.

4. Party B will be responsible for timely repair of waste wells, collapse, no water or substandard water due to quality problems.

5. If quality and technical problems occur within one year after the use of tube wells (warranty period), Party B will be responsible for free maintenance and solution.

6, in addition to Party A should bear the obligations of the second paragraph, not included in this contract, the other matters of the project are Party B is responsible for.

Eight, this contract is not exhaustive, the two sides can sign a separate supplementary contract, and this contract has the same effect.

Nine, this contract in quadruplicate, the two sides of the two copies, the date of signing effective.

Party A (official seal): _________ Party B (official seal): _________

Legal Representative (Signature): _________ Legal Representative (Signature): _________

_________ ____ ____ day _________ ____ month ____ Day

Well Drilling Contract Part 6

Party A:

Party B:

I. Well depth of 81 meters per meter yuan , total yuan.

Second, Party A deducts the well fee of yuan, quartz sand, deduction of yuan. Geotextile yuan.

Third, the well with other materials, Party B will bear the bamboo sheet wire cement and electricity costs yuan.

Fourth, the village mediation party A burden.

Fifth, all the safety on the frame of the accident by the party B burden.

Six, the amount of capital wells as deep as 80 - 81 meters wells are bad, by the party responsible for the B.

Seven, the amount of capital wells as deep as 80 - 81 meters wells are bad.

VII. After the well is finished, the site is cleaned up and left behind the materials deducted from the party B money.

VIII, Party A's total *** eye deadline lunar calendar day completion of the eye will not be settled in addition to the calendar.

Nine, the settlement method Party A paid to Party B in the support of each eye a settlement of payments five days before the completion of the completion of more than the completion of the settlement. Both sides of the above conditions to comply with each other A and B who default who bear the consequences.

Party A: Party B: Monthly