Traditional Culture Encyclopedia - Traditional festivals - Electric power engineering installation and civil construction with measures?
Electric power engineering installation and civil construction with measures?
In the construction project in the civil and electrical engineering is a very important part of the two, power installation and civil construction and there is a certain link, in order to ensure the quality of building construction must be the application of advanced civil construction and power installation technology, do a good job of both the mutual cooperation, and to take a series of practical measures for the prevention of the project to ensure the smooth progress of the project.
1 electric power engineering installation and civil construction with an overview
1.1 civil construction and electric power engineering installation relationship
Because of the installation of electric power engineering itself has a certain degree of specialization, the content of the work contained in the work are related to electric power work, such as cable laying project, power conversion and distribution works, electromechanical installation works. Civil engineering is a relatively independent construction project in the construction project, but in the development of civil construction programs need to take advantage of the actual situation of the power project, pay attention to some of the specifications of the power industry, so as to ensure that it can be properly constructed, to maintain the life safety of construction personnel. So the civil construction and power engineering installation in the engineering division is independent of each other, but in the engineering division and interlinked.
1.2 The significance of civil construction and power engineering installation
As a construction project in the construction of very important construction links, not only the power engineering installation and civil construction work is very important, the cooperation between the two is also very important. Civil construction and power engineering installation cooperation has an important role in the construction and operation of the building project. Electricity as the basic energy of human life, and people's life and work are closely related, and power engineering will also involve many industries. In the process of electric power engineering construction, installation construction work in the whole electric power engineering construction process is the largest degree of complexity and difficulty. So in order to ensure the safety and effectiveness of the project, we must ensure the smooth progress of the installation work. Once there are some construction problems, even some relatively small construction problems, will have an impact on the quality of the entire project. In the process of engineering construction, electric power engineering installation must improve the professional level of electric power installation staff, but also from the whole building design to make corresponding adjustments to ensure the quality of construction projects, to avoid a series of construction problems due to the installation of electric power engineering and civil construction due to improper coordination, resulting in prolonging the duration of the project, the construction cost increases.
2 electric power engineering installation and civil construction with effective measures
2.1 design preparation stage with the construction
Construction of the preparatory stage refers to the design period before construction, in order to ensure that the civil construction and electric power engineering installation of the coordinated application of engineering and technical personnel should do tacit cooperation, unity and cooperation to complete the scientific design of the drawings. Specific processes are: in the construction preparation stage, electric power engineering technicians need to get in touch with civil engineering technicians, in their respective fields to provide the project's specialized design requirements at the same time strictly check the rationality of the design drawings and implementability, and effectively avoid the later emergence of the conflict, for some unavoidable problems need to be found in a timely manner by the technicians and immediate communication to solve. Secondly, electric power and civil engineering technicians should y understand each other's construction progress and construction process, the cross work between the two projects to pay great attention to the area, to protect the smooth implementation of their own projects without interference. Finally, before the official start of civil construction, electric power engineering should be completed beforehand on the power pipeline buried, fittings and other processing, in order to prevent its adverse effects on civil engineering.
2.2 main construction stage with the construction
In the main construction stage of civil engineering, electric power engineering installers in the disposal of electric power buried parts should be in accordance with the efficiency of the civil concrete pouring, the specific progress of the project and other aspects of the comprehensive consideration, the handling of electric power buried parts are mainly manifested in the following points: first of all, in the process of building the template of the main structure of the civil engineering operation, the staff should pay attention to the relevant release line operation. Staff should pay attention to the relevant release operation, scientific determination of the safety of the components of the region and the set position of electrical equipment, and accurately locate the design drawings of switches, light boxes, drainage pipes and other equipment, in the implementation of the release process at the same time to set aside the appropriate size of the holes are not, for the construction of the latter part of the adequate preparation. Secondly, before laying the relevant pipeline, we should complete the assembly of the bottom reinforcement, sinking beam and other structures, and the location of the embedded parts to do the corresponding reinforcement disposal, and at the same time, reasonable setup and construction of pipeline through the beams, drainage pipes, and then in the implementation of sealing technology to carefully test the above process of the operation is in line with the specific provisions of the construction unit, if there are problems with the quality, appearance, performance, etc., the professionals should be improved in a timely manner in order to avoid more serious consequences. To avoid more serious consequences. The main problem is reflected in the lack of material performance, steel structure rust phenomenon, so it needs to be repeatedly verified before handing over the work, only to protect the quality and effectiveness of the above project, in order to lay a solid foundation for the construction of the later processing.
2.3 Installation stage with the construction
Electric power engineering installation work is not only the work of power engineering installers, but also need to assist civil construction personnel, power engineering installers and civil construction personnel **** with the installation of electrical equipment. In the process of electrical equipment installation, should be installed in accordance with the relevant installation system, especially civil construction personnel, because it is not a professional power staff, so it is prone to some work errors, when the civil construction staff with the power engineering installation staff have differences of opinion, must be based on the specific situation to analyze, and then to explore the installation plan that can solve the current problem, but also to Check whether the design of the reserved port meets the requirements, to ensure that the installation process can be safely and effectively put into use in the project after completion. In addition, the power engineering installation equipment and materials for the environmental requirements are relatively high, easy to be affected by external factors, which in turn hindered the installation of power engineering. For example, the cable is a common power installation equipment, widely used, and the quality of the cable is easily affected by external factors, restricting the safe operation of electrical equipment. Therefore, before construction, we should strengthen the supervision of electrical equipment and materials to ensure that the quality of electrical equipment and materials meet the requirements, so as to ensure the safe and effective installation of power engineering work.
2.4 Decoration link with the work
In the construction project, the interior decoration also directly affects the overall quality of the project, requiring perfect cooperation between electrical engineering installation and construction technology. At the same time as the interior decoration of the interior wall decoration will have a direct impact on the project, in order to ensure the integrity and safety of the project, should be repaired in a timely manner to repair the damaged area, and in the process of electric power engineering installation to determine the location of the building electrical installation, in a timely manner to check the location of the holes in the brush wall powder before the position of the interference, after the test to ensure that it meets the safety standards before being put into use. In addition, in the interior paint, spraying and other steps to achieve the installation of electrical equipment after the end of the civil engineering construction of the results need to be protected in a timely manner to prevent serious damage and to ensure that the electrical equipment is not contaminated.
2.5 Strengthen the completion of the test
Electrical installation in the late stage, electrical installation and civil construction staff need to carefully check the details, such as the key cable outlet to give protection, placement of cover, so as to avoid damage to the cable by the external environment; in the main control room and the installation of lighting personnel should communicate in a timely manner to fully understand the details, in order to determine the pre-buried pipelines, lamps and so on. Specific location. Secondly, before plastering, electrical personnel need to combine the pop-up level on the inner wall with the wall line to verify the information, to avoid errors, to ensure compliance with the requirements before the pipeline and box plastering treatment. In addition, electrical personnel also need to strengthen the maintenance of finished civil construction to avoid damage to the wall, when the installation of electrical equipment is completed, the installer should cooperate with the civil repair work to ensure that the performance of the electrical equipment to be played effectively.
2.6 Wrap-up link
In the power project is about to be completed, should be allowed to civil engineering technical responsible person and electric power engineering technical responsible person together with the inspection of civil construction work and electrical facilities installed. In addition, should organize civil construction workers unified repair due to the installation of power facilities or other elements of the damaged civil infrastructure, but also focus on the installation of power equipment in the process of each distribution room and the main control room, so as to ensure that the entire project construction to meet the relevant specification requirements.
3 Conclusion
In summary, in the engineering construction process, power installation and civil construction on the overall quality of the construction project has a direct impact, so in order to ensure the smooth implementation of the project need to do a good job of power engineering installation and civil construction work, from the engineering design program has been to the acceptance of the work process, the power installers must work closely with civil construction personnel, do a good job! Various steps of the work, it will not bring serious impact on the later construction, to ensure that the installation of electric power engineering and civil construction in an orderly manner, improve the quality of construction projects, and promote the long-term and stable development of China's construction industry.
More about the engineering/service/procurement category of the tender writing production, enhance the winning rate, you can click on the bottom of the official website customer service free consultation:/#/?source=bdzd
- Previous article:Why is gold so thin?
- Next article:Hefei "five bird play" into the school is how?
- Related articles
- What is the name of the flute accompanied by Bangzi Opera?
- Where is the fun in Shanghai in April?
- Traveling to the friend circle copywriting short
- The origin of the Dragon Boat Festival scented bag?
- Breeding techniques of bee beekeeping
- Difference between natural and regular garden in traditional garden
- Buma culture do virtual launch strength how?
- How about Fujian Mingta Toys Co., Ltd.?
- What are the interesting places in Shaoxing Yuecheng District? What interesting places are recommended in Yuecheng District of Shaoxing?
- What are the brands in Suqian Golden Eagle International Shopping Center?