How is the gypsum board fixed on the wall? Example of method flow
First, how to fix the gypsum board to the wall?
There are two kinds: first, bonded gypsum board wall, which has certain requirements for the flatness of the wall. Use bonded gypsum to dot the wall, and then paste gypsum board. The second type is: light steel keel facing wall, which is a bit complicated to do. If you are interested in this method, I can make a node diagram for you, which you can refer to the drawings.
Second, the gypsum board installation method
(1) construction process
Play ceiling elevation horizontal line → draw keel step line → install pipeline facilities → install main keel suspender → install main keel → install secondary keel → install gypsum board → brush anti-rust paint → install batten → install gypsum line.
(2) play a good ceiling elevation level
According to the floor elevation horizontal line, measure the ceiling elevation vertically with a ruler, and play the ceiling elevation horizontal line around the walls and columns.
(3) Draw the keel step line
According to the design requirements, arrange the spacing between the main keel and the secondary keel, and draw the keel step line on the level line of the played ceiling elevation.
(4) Install the main keel boom
After playing the ceiling elevation horizontal line and keel grading position line, determine the elevation of the lower end of the suspender. According to the position and hanging distance of the main keel, weld one end of the suspender without bolt thread with the embedded steel bar in the floor (expansion bolt can be used when the steel bar is not embedded), and brush the welding part with antirust paint.
(5) Install the main keel of light steel keel.
1, with boom nut.
2. Install hanger on the main keel.
3. Put the assembled hanger main keel into the corresponding hanger bolt according to the position of the step line and tighten the nut.
4, the main keel joint installation fittings, stay to adjust the elevation, arching straight.
5. Install additional main keels at the entrance of the cave, construct corresponding nodes in the atlas, and set up connecting fasteners.
6, nail edge keel, using nail fixation. When there is no requirement in the design, the nail spacing is? 1000? ㎜。
The above recommended example is about the design of the method and scheme for fixing gypsum board on the wall. In addition, there are descriptions of process steps and matters needing attention. From this, we can know that, generally speaking, in order to fix gypsum boards of various shapes and sizes on the wall, and to make the overall structure more beautiful and visually satisfactory, there are many places to pay attention to, including whether gypsum boards can not fall off easily as expected, and some spare parts for fixing.
Tubatu Online provides you with "every decoration quotation, 1-4 local decoration companies, 3 sets of decoration design schemes" and the decoration pit avoidance strategy for free! Click this link:/Zhu Ye /zxbj-cszy.php? to8to _ from = SEO _ zhidao _ m _ jiare & amp; Wb, you can get it for free ~
- Related articles
- Draft art lecture
- Medicinal parts of osmanthus fragrans
- Is erhu easy to learn? How long will it take to start?
- Dragon Boat Festival Customs in Shanwei
- I see a lot of people on the internet like to refer to Warcraft and Starcraft as RPGs, but my friend says that's wrong and they should be considered RTS games!
- Brief introduction of traditional festivals in China
- Why is the throne inherited by the first-born son? When was this tradition first established?
- Request translation into English-urgent
- What are the customs of the winter solstice festival?
- What is the main study of Chinese medicine pharmacy major