Traditional Culture Encyclopedia - Traditional stories - How to do waterproof construction of linoleum coiled material roof
How to do waterproof construction of linoleum coiled material roof
Technical requirements for waterproof construction of linoleum coiled material roof: the waterproof layer can only be laid after applying cold priming oil for one day and night. When paving, the heating temperature of hot asphalt methyl telluride ester should be ≤240℃, and the service temperature should be ≥ 190℃. Asphalt methyl telluride ester should be evenly daubed, not too thick or piled up.
Thickness of bonding layer: hot asphalt mastic should be 1 ~ 1.5 mm, and cold asphalt mastic should be 0.5 ~1mm; Thickness of surface course: hot asphalt mastic should be 2 ~ 3 mm, and cold asphalt mastic should be1~1.5 mm.
Coil laying direction: when the roof slope is less than 3%, the coil is laid parallel to the roof ridge, and when the slope is 3% ~ 15%, it can be parallel or vertical to the roof ridge, and the slope is >; L5% must be perpendicular to the roof pavement.
- Previous article:Which area is famous for its bamboo weaving art
- Next article:Teacher Zhao's speech to volunteers who often accompany him.
- Related articles
- Re-examine the "35-year-old threshold" of the job market. How to treat the employment threshold of 35 years old?
- Moon cake composition 300 words
- Hospitals above the second level in Jiangsu will fully implement appointment diagnosis and treatment.
- Shaolin Temple Wenwu School how much tuition to pay a year
- Introduction to the characteristics of slab high-rise buildings?
- How to Develop Family Style Family Training Activities
- What's the name of yoga?
- How to draw the border of the bookmark
- Who are the famous Henan Opera artists?
- The History and Culture of Murals