Traditional Culture Encyclopedia - Traditional customs - Construction method and matters needing attention of cement concrete floor

Construction method and matters needing attention of cement concrete floor

Cement concrete floor is one of the common floor decoration methods. This kind of decoration is easy to build, and parking lots and factory workshops are the most common. Although many people don't like it, it is very practical. So, how to make the cement concrete floor look good? Next, Bian Xiao will discuss the construction details of cement concrete floor with you.

First of all, how to pave the cement concrete floor?

1, cement concrete floor construction is not like other floors. First of all, the soil must be kept moist. Therefore, before leveling the building, water must be sprinkled on the ground to make the building ground permeable. The solidified soil is not easy to break. If the speed is not enough, it will directly affect the adhesion between cement and grass.

2. Cement can't be directly used to open the package, but must be mixed with sand in a certain proportion. Only the right mixing ratio is difficult to crack; If the ratio is too low, the cement floor seems to return to sand and ash, which can be remedied but annoying. In this case, it is suggested that the cement-sand ratio should be controlled at 1:? 4- 1:? Between 5; If it is fine sand for home decoration, the proportion should be adjusted to a higher proportion.

3. Mix the mortar evenly and pay attention to the consistency of the whole process. Because the difference of viscosity will affect the actual effect of cement solidification. If the mortar is thick, the shrinkage of cement surface is small, and the sand is thin, it is easy to have height error, which leads to uneven terrain, so removing the mortar is a very important step.

4. If the cement concrete floor is uneven, we should soften it immediately before the cement solidifies. In particular, it takes time to measure the height difference, and it is necessary to start pulling wires when the cement is initially set. The leveling process must control the time and difference. I would like to remind you that leveling cannot be repaired after the mortar is solidified.

5. After the floor is paved, specific maintenance work should be carried out; Do not water for 2-3 days after the training; Then, spray water 2-3 times a day to make the cement naturally dry and not easy to break. When building soil, we must control the ambient temperature, otherwise the cement will dry easily too quickly.

6. Let the concrete floor have a transparent light effect, and it will also be calendered. Calendering requires people to operate on the ground. So before people stand up and start working, they must wait for the cement floor to dry and solidify for 4-5 hours.