I knelt down and begged the template of the temple repair construction organization design. Thank you for offering it.
The first chapter is the compilation of general instructions
I. Compilation Description
As the construction party of this project, our company independently compiled the construction organization design of a temple building project by carefully studying and analyzing the construction drawings and listening to the opinions and suggestions of relevant ancient architecture experts. This construction organization design covers all the engineering contents within the construction scope included in this project in the construction drawing-civil engineering, installation and supporting projects. This paper focuses on the idea of unified management of the engineering quality, time limit, safety, civilized construction and service coordination of a temple construction project from the perspective of the engineering contractor, with a view to fully fulfilling our responsibilities as a contractor with high quality and high efficiency.
In order to effectively guide the construction and serve the excellent projects in the future construction process, before compiling, our company conducted a detailed survey of the construction site, organized relevant personnel to study the relevant laws and regulations of the country, Zhejiang Province and Wenzhou City, fully understood the local architectural characteristics and market conditions, became familiar with the engineering drawings, studied the bidding documents, and mastered the scope, region and management responsibilities of our construction; In the preparation process, our company was fortunate to invite relevant experts to guide our preparation work for many times, and the experts put forward a lot of valuable, scientific and practical suggestions, which enabled our company to formulate the construction organization design in a targeted manner in combination with the characteristics of this project; Here, I would like to express my heartfelt thanks to all the experts for their attention! This construction organization design introduces in detail the construction scheme and construction technology of the main partial projects involved in a temple construction project.
According to the characteristics of this project imitating the Tang Dynasty, combined with the construction difficulties of this project, and fully considering the social importance of this project, the main structure and decoration project construction scheme are emphatically introduced in the construction scheme designed by this construction unit. In terms of management, the construction organization guarantee system, the allocation of labor and machinery, and the measures of time limit for a project, project quality, safety, civilized construction and comprehensive coordinated management are expounded in detail. At the same time, in this construction organization design, our company has made various commitments to the project return visit and maintenance service, which will be included in the construction contract as contract terms, making it have corresponding legal effect. Our company promises to send the project manager and technical director with rich experience in similar projects to lead the construction management personnel who have cooperated closely for many times to the site; All construction management personnel must hold relevant certificates. During the construction process, our company will continuously assess their work to ensure the management level of the project construction. In order to ensure the realization of the goal of "creating excellent products and creating high quality", our company will conduct management in strict accordance with the requirements of ISO9002 quality certification system, and regularly send personnel to the site for inspection and assessment of on-site management.
Second, the compilation basis
The building project of a temple is compiled in accordance with ISO 9000: 2000 standard and relevant company regulations, relevant construction acceptance specifications of the project, national quality inspection and evaluation standards of construction projects and ancient buildings, drawings of the construction unit and national and local regulations on construction site management, which serves as a guide to guide the whole process of construction management.
Mainly based on literature:
1, construction drawings of a temple building project
2. Safety code for power supply and use in construction sites
3, the construction site temporary electricity safety technical specification "
4. Unified standards for quality inspection and evaluation of construction and installation projects
5, "building engineering quality inspection evaluation standard"
6. Technical Specification for Safe Use of Construction Machinery
7. Technical Specification for Building Foundation Pit Support
8, "building construction safety inspection standard"
9. Code for Construction and Acceptance of Masonry Engineering
10 concrete strength inspection and evaluation standard
1 1, quality inspection and evaluation standard for ancient buildings.
12, Code for Construction and Acceptance of Building Ground Engineering
13, the original law of ancient building construction
14, Code for Construction and Acceptance of Ancient Buildings
15, China landscape architecture technology
Three. Project objectives and commitments
1. Project quality objective: to ensure excellence and strive for Oujiang Cup.
2. Project progress: ensure that the construction task of this project is completed within 153 calendar days and delivered to the owner on time.
3. Engineering safety: put an end to heavy casualties in the whole construction process.
4. Civilized construction: create a first-class construction site and strive for a standardized construction site with safety and civilization in Wenzhou.
5. On-site arrival rate: 80% for the project manager and 90% for other managers.
Chapter II Project Scope and Characteristics
I. Scope of the project
Civil engineering, installation and supporting works within the scope of the construction drawing of this bid. The scope is to build the Ursa Major Hall and the Heavenly King Hall on the central axis first, and then build other buildings.
Second, the project overview
(1) Brief introduction of all parties.
Construction unit: Wenzhou Huguo Temple Construction Engineering Office
Designer: Zhejiang Institute of Ancient and Modern Landscape Architecture
(2) List of construction projects
Shimen: made of all stone.
Archway: four-column and three-room structure, reinforced concrete frame structure.
Seven Tathagata: Seven granite pagodas. There are reliefs and sumeru in it.
Shanmen: The overall width is 15.0m, and the depth is 2.7m There are three arched buildings on the fifth floor, which are pavements.
Bell and Drum Tower: Located in front of the Heavenly King Hall, on the east and west sides of the central axis. The plane is square, and the second floor rests on the top of the mountain. Reinforced concrete frame structure.
Ursa major: seven rooms are 3 1.5 wide and five rooms are 22.5 deep. Its column network consists of inner and outer sides, forming the form of inner and outer grooves with five widths and three depths. The back of the inner groove is equipped with a Buddhist altar, and the eaves column is equipped with seven buckets. The roof adopts four double eaves (that is, the roof of the palace) and is covered with cyan pottery tiles.
Tibetan Scripture Building: located behind the Jade Buddha Temple, it has two floors, seven rooms and five entrances with a flat roof, a gallery on the ground floor, and six eaves and columns paved with double arches. Both sides of the sutra building are connected with the wing through the corridor.
Jade Buddha Hall: five rooms and four doors, with a total width of16.4m and a depth of12.0m ... with a single eaves roof.
Yakushido: The overall width is 1 1.7m, the depth is 8.4m, and the roof is suspended from the mountain.
Fatang: Five rooms with three entrances, width17.4m, depth10.8m ... single-eaved hilltop building.
Wing: Double-slope roof on the second floor, front eaves cloister.
Abbot courtyard: a three-in-one courtyard combination, the main building is a sloping hill top, with two floors in total. There is also a porch, with a yard in the middle and a pool mountain in the yard.
Tower: A five-story pavilion-style tower with a square plane and stairs inside.
This time, we will build the Hall of Ursa Major and the Hall of the King of Heaven first.
Three. Description of engineering features:
A temple is located on a mountain pier surrounded by jungle in Jingshan Park, southwest of Wenzhou. The landform of the temple site is complete, facing mountains in the west and southeast. The terrain is flat, with the lowest elevation of 44.0 meters in the east and the highest elevation of 57.9 meters in the west. It is a gentle slope with a low east and a high west, forming a trend of increasing step by step, which can be described as a treasure house of world traditional famous temples.
Huguo Temple was built in the Tang Dynasty from Zhenguan to the Five Dynasties in Hou Liang. It has a history of more than 1000 years, and has the reputation of protecting the country and peace at home. It is a famous temple in southern Zhejiang, the largest Buddhist jungle in our city, and the former site of the earliest Buddhist college (formerly known as Shanjia Lecture Hall) in southern Zhejiang. There are many cultural relics and historical sites in the temple, and there are many great virtues of eminent monks in the past dynasties: Master Yan became a monk in the Song Dynasty to protect the country, and in the 1930s he was able to become a monk and abbot to protect the country. His disciples Xiang Xian and Guan Yu were both famous eminent monks, and the word "temple to protect the country" was written by the master. In order to further implement the Party's religious policy, enrich the cultural connotation of Ouyue, protect cultural monuments, carry forward China's long-standing Buddhist cultural tradition and improve Wenzhou's urban cultural taste, the restoration and expansion of Huguo Temple has been put on the agenda.
(1) natural features:
Wenzhou has a subtropical monsoon climate with four distinct seasons, each with its own characteristics: rainy spring, rainy season in May and June, high temperature season in summer in July, August and September, typhoon rainstorm in September and1October, and the winter construction period is generally 80 days in March of the following year. The annual maximum temperature can reach 39 degrees, the minimum temperature can reach -5 degrees, and the annual rainfall is 1500mm. The construction period of this project is from June 2003 to June 2004 10, and the construction will go through rainy season and summer.
(2), regional characteristics:
The project is located at the foot of Jingshan Mountain in Wenzhou, with mountains in the west and southeast. The terrain is flat and the overall environment is superior.
(3), building structure design:
Virtual and real architecture, complexity and simplicity, decoration and color, whole and part, etc. , are included in the overall unity. Considering the overall effect, architectural creation should keep the center of gravity of the building on the central axis, fully reflecting the absolute prominent position of its main building. The design takes the Uruguayan temple as the main body of the temple, and other buildings should take it as a measure in terms of volume, scale and form to avoid usurping the role of the master. The detailed design of the building combines the practices of Jiangnan and the customs of Ouyue, making the building look lively and light. Such as "hair", "ang" and "tail" in the corner.
The overall style of architecture in the Tang Dynasty is characterized by the gentle slope of the roof, the gentle slope of the eaves and the thick tail, which makes the whole facade present a solemn and steady image. The ratio of bucket arch to column height is close to 1: 2, and it feels that the scale of bucket arch is extremely huge. This proportional relationship shows the stable and magnificent style of architecture in the Tang Dynasty.
(1) Daxiong Hall and Tianwang Hall are single-story and double-eaves. The multi-column structure is designed with reinforced concrete frame structure, and the columns and upper concrete beams are cast-in-place roof structures. Considering the building requirements, the main components such as beams, purlins, rafters and risers are cast-in-place reinforced concrete, which are integrated with the roof.
(2) The Sutra Collection Building, Drum Tower, Bell Tower, Bell Tower, Abbot Building, etc. There is a heavy load, and the structure is a concrete beam slab.
(3) Cast-in-situ reinforced concrete is used for the fish pond flying beam, waterproof concrete is used for the bottom and wall of the pond, reinforced concrete columns are erected in the middle of the pond, and bridge decks are erected. Let tourists stroll to enjoy the fish and communicate with Shanmen, Tianwangtang, Drum Tower and Bell Tower. The pool is separated from the foundation of the surrounding buildings, and settlement joints are set. When designing, we should carefully consider the relationship with the surrounding foundation, the inclination and uneven settlement of waterproof foundation.
The archway is cast-in-place with reinforced concrete, and the side is provided with drum stones to ensure the lateral stability of the archway. The upper part of Tathagata is stone, and the foundation is cast-in-place reinforced concrete.
(4) General living facilities are considered as ordinary civil buildings. Generally, brick walls with small holes are used to bear the load in the form of masonry structure, and structural columns and ring beams are added in the walls to enhance the integrity of houses and improve their seismic capacity. For large bays, load-bearing columns and beams can be set.
⑤ Huguo Temple is an ancient architectural complex with reinforced concrete instead of brick and wood structure. The order of column, beam elevation and column height must be interrelated. Roof slopes, cornices, beams, purlins, rafters, etc. It is criss-crossed and must be well connected with the roof panel. The design basically adopts cast-in-place form, which enhances the integrity of the house, but also increases the difficulty of construction.
⑥ The roof is made of tile, pipe tile and other materials, which are heavy and should be fully considered in design.
All buildings have no settlement joints and expansion joints.
(4), construction conditions:
The construction site has been basically leveled. The survey datum is provided with the assistance of the owner. After the road enters the site, it is necessary to pave the road along the designed permanent road to ensure the smooth traffic in the site. Water and electricity have been put in place and the supply is sufficient.
(5), time limit for a project and quality:
Project date: the principle is that the project should be completed before June 65438+1October 3 1 in 2004, so as to leave enough time for the greening construction unit to complete all the projects before the end of 2004. According to our own strength, our company plans to start construction on June 1 day, 2003, with a calendar period of 480 working days, so as to ensure the completion on June1day, 2004.
Project quality: ensure the overall quality of the project and strive for Oujiang Cup.
Chapter III Construction Deployment
This project is the reconstruction of ancient buildings, which is a new building imitating the Tang Dynasty. It involves not only the protection of cultural relics and the reconstruction of wood structures, but also the application of some modern structures and practices in antique buildings. According to Article 14 of the Law of People's Republic of China (PRC) on the Protection of Cultural Relics, the principle of not changing the original state of cultural relics must be observed in repairing, maintaining and moving ancient buildings. During the construction, based on the current surveying and mapping research, the original overall style of the building was restored; Make full use of the original materials of the building and adopt similar materials and construction practices for the parts that must be replaced; It is speculated that the recovery part should be basically consistent with the practice at that time. Improve the fire, corrosion and insect resistance of wood in maintenance. In modern architecture, it should conform to the current relevant national standards.
First, the construction preparation
(1) Site handover preparation
After the completion of our model project, our company will send relevant personnel to the construction site within 3 days after receiving the bid-winning notice to prepare for the on-site handover. The key point is to review control points, control lines, elevations, etc. , and adjust the existing construction site to make the whole site conform to the layout principles and requirements of our company. These work plans are completed before entering the site.
(2) Technical preparation
From the date of entry, technical preparations will begin immediately. On the one hand, relevant personnel can read the construction drawings carefully and understand the design intent and related details; On the other hand, technical preparations such as steel bar sample, woodworking sample, masonry sample, concrete grading test, blue prints.the design, technical disclosure, etc. At the same time, more detailed construction work instructions will be compiled according to the construction needs, so that the project will be controlled by technical management from the beginning, thus ensuring the quality of the project.
(3) Machine preparation
After the medium and small machines and tools enter the site, they will enter the site in batches according to the site plan, and they will be maintained by special personnel. All the equipment entering the site is in the best running state.
(4) Material preparation
Our company will provide the amount of steel and cement in time according to the double sample list and concrete grading list, and submit it to the owner for filing, and implement other related material suppliers for the owner's approval. At the same time, carry out the procurement work organized by our company, and timely organize the early turnover materials to enter the site to ensure the smooth construction.
(5) Personnel preparation
Within 3 days after receiving the bid-winning notice, the project team, the personnel of the general contracting management department and relevant personnel will immediately enter the site to prepare for the preliminary construction and assume the management responsibility of the general contracting. 10 before the start of construction, all the construction management personnel are in place, and the construction personnel enter the site in batches according to the needs of the site. The company is equipped with enough professional construction operators.
Second, the construction organization
Construction organization is mainly divided into five parts: personnel organization, mechanical equipment organization, material organization, transportation organization and coordination organization. Whether the content arrangement of these organizations is reasonable will directly affect whether the whole construction and production process can be successfully completed. Therefore, according to the internal coordination of various departments of our company, the arrangements of these five institutions are mainly as follows:
(A) the project team configuration and management system
The importance and management mode of this project determine that managers must have high professional quality. When establishing the project management team of this project, our company will send a project management team with rich construction experience and similar ancient buildings to the site to directly participate in the construction and management of this project.
In the construction management of this project, the construction will be organized in strict accordance with the project law and the general contracting responsibility system will be implemented. In terms of department setting, all functional department personnel from commencement to completion will be provided to ensure the continuity of the whole project in the whole construction process. The technical, quality, safety, materials and other functional departments of the company strictly follow the inspection requirements of the company's project law, and regularly go deep into the project to effectively supervise, guide, control and serve the project, creating good conditions for comprehensive management, coordination and control. See the chart on the next page:
(2) Labor deployment plan
The construction service layer is the actual operator in the construction process and the most direct guarantor of construction quality, progress, safety and civilized construction. Therefore, our company's principles in selecting service-level operators are: choose from the list of excellent service personnel in our company; Good quality and safety awareness; Have a high technical level of ancient buildings; Construction personnel with similar engineering construction experience.
The service layer is divided into three categories: the first category is highly specialized technical jobs with about 20 employees, including mechanics, mechanics, maintenance electricians, welders, scaffolders, experimenters, surveyors, etc. These employees have participated in the construction of similar projects in our company with rich experience and hold corresponding post operation certificates. The second category is ordinary technical jobs, with an average of 75 people, including carpenters, bricklayers, masons, painters, steel workers and concrete workers. They built a similar project, which was mainly organized by three ancient architectural technicians as a guide. The third category is unskilled jobs, with about 25 people. The source of such personnel is the established construction labor team that has cooperated with our company for a long time, and the personnel entering the site have certain quality. The peak number reached 120, and the average value was 100. In the future, if the engineering quantity increases, the personnel will change according to the change of engineering quantity.
According to the monthly workload, schedule and quality requirements of the project department, the human resources department of the company will organize the selection and determination of experienced labor teams with the ability to construct ancient buildings, handle various employment procedures and make balanced deployment throughout the company to ensure the smooth progress of the construction.
(3) mechanical equipment configuration plan
(1) basic stage
The foundations of Daxiong Hall and Tianwang Hall of this project have been completed, and other building foundations are planned to use self-mixed concrete to meet the needs of the project. According to the requirements of the owner and the actual situation on site.
(2) the main stage
This project adopts self-mixed concrete and manual vertical transportation.
(3) Decoration stage
Decoration construction stage: mortar for masonry and ground leveling is mixed with sporadic concrete at the centralized mixing point, and a J 1-400 mixer and two mortar machines are equipped. Horizontal transportation is equipped with two 1t small dump trucks and trolleys on the ground.
At present, the above equipment is undergoing comprehensive repair and maintenance, and will be transported to the construction site for installation, debugging and use at any time.
List of main mechanical equipment of this project
Serial Number Equipment Name Model Specification Quantity Equipment Capacity Input Time Remarks
1 concrete mixer J 1-400 2 Loading capacity 0.4m2 June 2003.1
2 mortar mixer UJZ 200 250m3/m3 2003.6. 1
3 steel bar cutting machine GJ40 1 1 machine-team/machine-team 2003.6. 1
4 Steel bending machine GJ4011June 2003.1
Five-sided planer MPF-5ac2 1 machine-shift/machine-shift 2003.6. 1
6 voltage plan MJ 104 1 1 affecting/station 2003.6. 1
7-angle cutting machine MC-4 6 1 Machine tool shifting/setting June 2003 6438+0
8 welder: 1-330 1 1 machine shift/unit: June 2003.1
9 excavator sh 140 1 1 machine-team/machine-team 2003.6. 1
10 vibrator Hz-50 10 1 affecting/Taiwan June 2003.1
1 1 other handheld 2003.6. 1
Lighting 2003.6. 1
13 25 tons of automobiles June 2003 1
14 automobile 2 10 ton 2003.6. 1
15 needs to be equipped with 10 car. 2003.6. 1
(4) Reusable material deployment plan
The organization of raw materials is mainly divided into two categories: the first category is self-purchased materials, and our company will shop around to check the quality and unit price, and then purchase them after approval by the owners and relevant departments; The second kind of materials will be purchased by the construction unit, and our company will conduct quality inspection on the materials entering the site under the authorization of the owner.
The turnover materials used in this project are processed and customized in time by the project management department and the company's materials department, and adjusted and supplemented according to the schedule to ensure the smooth construction of the project.
See the list of reusable materials and equipment for details.
You can't. Specification requirements for reusable material names Quantity Source Remarks.
1 steel pipe φ48 260 tons lease
2 The cross, butt joint and rotation of fasteners is RMB 6,000.
3 Bowl-buckle scaffold with three supports and two plates 1 set comes with it.
4 scaffolding 50x300x4000 70 purchase.
5 adjustable bracket φ 50 50 sets have their own.
6(50x 100 x4000 50m 3 purchase.
7 bamboo plywood 915x1830x18100 sheets.
8 steel formwork 300 x 1500 250 x 1500
150x 1200 Other modules * * * 200m2 lease.
9 Mimu Safety Net 1.8 MX 6m 6 100 for purchase.
(5) Site and transportation organization
This project is located in Jingshan, Wenzhou City, and the site construction land has been surrounded by temporary walls, so the surrounding environment needs to be protected. Therefore, the site transportation organization follows the following principles:
A, in the construction preparation stage, the subgrade is laid on the designed permanent road as the on-site transportation road to avoid unnecessary repeated construction.
B, in the whole project construction stage, the site set up production area, office area, living area, tool room and safety facilities. Make full use of the facilities provided by the owner or the abandoned houses left before.
C, the site is divided into three stages in time: the first stage is measurement and cleaning, and the exposed reinforcement of the foundation is derusted; The second stage is the concrete main body construction; The third stage is interior and exterior decoration. Give full consideration to the location of materials, and arrange them at multiple points in a centralized way to reduce the secondary movement of materials at the site.
(six) coordination with the owner, supervision and design institute
If our company can win the bid to undertake this project, it will put the coordination and organization work in an important position. The internal coordination management of the project is mainly determined around the construction itself, including the coordination management among the owner, the designer and the supervisor. The project manager department is responsible for coordinating and managing the quality, safety and civilized construction and construction progress of the construction team, providing reasonable construction working surface for each construction team, coordinating the connection of each process, providing water, power supply, existing vertical transportation equipment, existing scaffolding and necessary office and storage conditions, thus creating favorable conditions for the overall construction of this project.
A, coordinate with the owner.
Coordinating the relationship with the owner is a key point of the project management department. Through good cooperation, we can ensure the full performance of the project contract, which is mainly manifested in: attending regular meetings with the owners to discuss and solve various contradictions and problems in the construction process and straighten out the relationship at various stages; From the construction point of view and previous construction experience, and for the sake of the owner in the construction, meet all kinds of reasonable requirements put forward by the owner, so as to establish a harmonious relationship.
B. coordinate with the design institute.
Cooperate with Zhejiang Ancient and Modern Landscape Architecture Research Institute to ensure that the project can meet the designer's ideas and requirements and the quality requirements of relevant national codes and regulations. Its main manifestations are as follows: introducing the construction situation and construction technology to designers on a regular basis; Before the construction of each sectional project, submit the construction scheme or work instruction related to the designer and listen to the opinions of the designer; Exchange our opinions on the design content, and improve the design with our rich construction experience to achieve the best results. And invited a chief designer of the design institute to revise and improve the construction drawing on the spot.
C, coordinate with the supervision unit.
Work closely with the supervision unit to jointly control the quality of the whole project and supervise and inspect the whole construction process. Before the construction of each subdivisional work, we will submit relevant construction plans or work instructions and listen to the opinions of the supervisor. When the supervisor implements the supervision work, we should not only insist on its independence, but also provide necessary convenience for it to implement the supervision work and cooperate with the supervisor to do the supervision work well.
D. external coordination organizations
We attach great importance to the construction of this site, cherish this opportunity, and establish a good image of our company in this site. Here, we will clearly set up a special coordinator in the organizational structure of the project to be responsible for the external coordination of the project during the construction process, and take it as the key work of the project to ensure the smooth construction of the project and realize all the indicators we promised.
The external coordination in the construction process is extensive, which is mainly divided into two parts: the coordination of residents around the construction site and the coordination of various competent departments of Wenzhou Municipal Government.
Managers with strong civil coordination ability went deep into nearby police stations, neighborhood committees, traffic police and other relevant departments, and communicated with the police, traffic police and residents through forums and other forms.
Regarding the coordination work of Wenzhou municipal government departments, we will sort out our thinking, list whether each link in the construction is related to the government departments, and contact the relevant departments of Wenzhou municipal government in time to make the work ahead and make the foreign coordination work in a more active position. In the coordination work with the competent department of Wenzhou municipal government, we should also communicate and understand in time, gain mutual understanding and trust with the competent department of Wenzhou municipal government, and make contact through various forms such as symposiums, consultation meetings and study meetings. According to our previous construction experience, these departments are mainly: Buddhist Association, quality supervision station, security inspection station, sanitation department, municipal department, public security bureau and its subordinate police stations, power supply department, water supply company, health and epidemic prevention department, construction management department, fire station, traffic police force, city appearance supervision department, etc. Respect their opinions on site management, go through relevant formalities according to regulations, strengthen construction site management, ensure the smooth construction of the whole project, and ensure the quality on time.
- Related articles
- Development form of project roadshow
- How to make Mid-Autumn Festival bookmarks beautiful, simple and lovely?
- E-commerce and information systems are different _ e-commerce and traditional business similarities and differences
- What does the production budget include?
- Suzhou Seals moved to provide professional air-conditioned shuttle service.
- What festival?
- How about Beijing Baojun Academy?
- What are the specialties in Ganzhou, Jiangxi?
- What international competitions are there?
- What do you think of China's long currency culture by explaining the history of currency development?