Traditional Culture Encyclopedia - Traditional stories - Hello, I would like to ask what licensing procedures are needed in the early stage of 1 10KV substation construction. Do you have a minute? Thank you for your trouble.

Hello, I would like to ask what licensing procedures are needed in the early stage of 1 10KV substation construction. Do you have a minute? Thank you for your trouble.

Hello:

The question you asked is very simple, and it is not easy to answer directly! The general contents are as follows:

First of all, the construction of 1 10KV power station must conform to the national industrial policies, such as low energy consumption and high efficiency of factories and mines. If it is high pollution and high energy consumption, I believe the country will not allow you to set up a project. This is a prerequisite!

Secondly, the electrical equipment installed by your company meets the standard of 1 10KV power station. If the installed load is small, the power company will not give you such a power station. As far as I know, the main transformer of 1 10KV power station should be above 4MW. If it is less than this load, 35KV or 10KV power station should be considered. To put it simply, it is unnecessary for enterprises to build 1 10KV power station. This is to confirm the corresponding voltage level according to the installed capacity of the enterprise!

Secondly, the area where factories and mines are located is affected by the power distribution of power supply companies. It depends on whether the power grid can provide you with the load of the voltage level you need. Simply put, it is whether the power grid can withstand the power you want. This is a comprehensive problem of economic indicators and load distribution, which cannot be decided by enterprises!

Simply put, you can go directly to the business hall of your electric power company for consultation, fill in the relevant application form for electricity consumption and submit it to the corresponding electric power department. But this is really just the beginning. The relevant personnel of the power department will contact you, and then you can do it according to the requirements of the power company! There are still many formalities to be done later!

Or call 95598 for consultation, and he will tell you exactly how to do it!