What are the approval processes for project construction?

Construction projects from project initiation to completion include the following procedures: project approval, planning and design, application for construction projects, and completion acceptance of construction projects.

First, the project approval, this stage needs to be submitted:

1, original project application report.

2, the project proposal or project feasibility study report

3, construction land ownership documents or construction project land pre-trial opinions.

4, the project construction investment budget

5. Original capital certificate issued by the bank credit department.

6. A copy of the business license of the enterprise as a legal person.

7. Topographic map of the project

Second, the planning and design stage includes the following steps:

1, the planning and design conditions are provided by the Municipal Planning Bureau according to the survey and design red line issued by the overall urban planning and project documents.

2. Three stages of architectural design: scheme design, preliminary design and construction design.

3. Finally, the Urban Construction Bureau is responsible for contacting the relevant municipal departments to reply to the preliminary design review.

Third, the construction project construction

(a) construction projects, first of all, to provide the following information to the Construction Committee for registration:

1, Fixed Assets Investment License issued by the planning department.

2 construction land planning permit and construction project planning permit issued by the planning department.

3. State-owned land use certificate issued by the land department.

4. Review and approve the construction drawings and construction drawing design documents designed by design units that meet the project design qualification.

5, issued by the civil air defense office "civil air defense engineering construction permit"

6, issued by the fire department "building fire design audit opinion"

7, lightning protection facilities design audit issued by the lightning protection facilities testing institutions.

8, issued by the earthquake office "seismic fortification audit opinion"

9. Proof of construction funds

10, the approval of the project budget and construction project category issued by the cost department.

1 1, other information stipulated by laws and regulations.

(two) to handle the quality supervision of construction projects, it is necessary to provide the following information to go through the formalities at the quality supervision station.

1, planning permit

2, the project construction bid-winning notice or the project construction contract approval form.

3, the engineering supervision bid-winning notice or the engineering supervision contract approval form.

4, the construction contract and its unit qualification certificate copy

5, supervision contract and its unit qualification certificate copy

6, construction drawing design documents review and approval

7. Application Form for Quality Supervision of Construction Project

(three) to handle the safety supervision of construction projects, it is necessary to provide the following information to go through the formalities at the safety supervision station:

1, information provided by the construction unit:

(1) Project Construction Safety Supervision Report

(2) The bid-winning notice of engineering construction or the approval form of engineering construction contract.

(3) The bid-winning notice of project supervision or the approval form of project supervision contract.

(4) Engineering Geological Survey Report (Conclusion)

(5) Construction drawings (including elevation, vertical and profile of basement)

(6) Project budget (total construction area, number of floors, total height and cost)

2, the information provided by the construction unit:

(1) Responsibility system for safe production and civilized construction

(2) Management objectives of safe production and civilized construction

(3) Construction organization design scheme and special technical scheme

(4) Safety production and civilized construction inspection system

(5) Education system of safe production and civilized construction

(6) A copy of the qualification certificate of the project manager, and the original and copy of the work certificates of safety officers and special operations personnel.

(7) site facilities, safety signs and other general layout.

(8) Purchase the original and photocopy of the safety net certificate and invoice.

(9) Responsibility Letter for Construction Safety of Building Engineering

(10) Application Form for Construction Safety Supervision of Construction Project

Four, to receive the "construction permit"

Extended data:

First, the construction project completion acceptance?

When the construction project is completed and accepted, the following materials shall be provided to the quality supervision station for review, and the quality supervision station shall complete the review within 7 working days.

When the construction unit organizes the relevant units for acceptance, the quality supervision station will send personnel to supervise on the spot. ?

1. Completed engineering design and contents agreed in the contract.

2, the project completion acceptance application form

3, the project quality evaluation report

4, survey and design documents quality inspection report

5. Complete technical files and construction management data (including equipment data)

6, the main building materials, building components and equipment used in the project approach test report.

7, foundation and foundation, the main concrete structure and important parts of the inspection report

8. The construction unit has paid the project payment according to the contract.

9. The project quality guarantee signed by the construction unit

10, municipal infrastructure related quality inspection and function test data

1 1, planning acceptance certificate issued by the planning department.

12, public security, fire protection, environmental protection, lightning protection, elevators and other departments issue acceptance opinions or acceptance certificates.

13, the problems ordered by the quality supervision station to be rectified have all been rectified.

14, project completion settlement book issued by the cost station.

Two, before the completion of the construction project acceptance, the construction unit shall provide the project construction safety evaluation issued by the safety supervision station to the Project Construction Committee.

Three, the construction project completion acceptance for the record, from the date of the project completion acceptance 15 working days, provide the following information to the quality supervision station for the record.

Four, the construction project completion settlement audit