Traditional Culture Encyclopedia - Lucky day inquiry - The daywork plan includes all kinds of labor, but it should not include materials and construction machinery.
The daywork plan includes all kinds of labor, but it should not include materials and construction machinery.
The daywork plan includes all kinds of labor, but it should not include materials and construction machinery. This sentence is wrong.
Definition of the concept of daywork: refers to the fees paid by the employer to the contractors involved in the project construction to complete the work unrelated to the project.
Although daywork is called daywork, it actually includes labor costs, materials, tools, machines and even mechanical equipment that people carry to complete their work.
The daywork shall be priced according to the comprehensive unit price, and shall be included in the total bid price when bidding.
The daywork plan includes labor, materials, machinery and their notes and totals. Labor, materials and machinery are priced at the comprehensive unit price.
Daywork is suitable for piecemeal settlement, which generally refers to extra work that is not stipulated in the contract or caused by changes and has no corresponding items in the bill of quantities, especially those that are not allowed to agree on the price in advance.
According to the bidder's own ability and experience, and according to the content of engineering quantity in the preliminary work list, the bidder will make an independent quotation, including labor hours, related expenses corresponding to the number of materials and the number of construction machinery shifts, as well as management fees and convenience of cooking.
When calculating the hourly wage payable to the contractor, the working time shall be calculated from the day when the workers arrive at the construction site to engage in the daily tool project until they return to their original departure place. But it does not include meals and rest time. Only when the workers' team directly engages in the work designated by the engineer and is competent for the work, the working hours of the monitor who actually works with his team should also be counted.
But it does not include the working hours of foremen and other supervisors. The contractor has the right to get all the time expenses of the services employed by the daywork, and calculate the basic unit price and the additional percentage of the basic unit price filled in the contractor's daywork unit price table as the contractor's profit and management fee.
- Previous article:What's the point of the film "The Great Protector"?
- Next article:Zodiac order table, how to specify the order of zodiac?
- Related articles
- Is it a good day to start the twelfth lunar month in 2022?
- I don't know classical Chinese. I don't know which expert can help me translate!
- 202 1 where is the location of the god of wealth on the fourth day of the first month?
- Gifts and daily necessities
- An Zao Ji ri
- Where is Changji Monday episode?
- Can a chicken man and a snake woman get married in August 1 day?
- What is the relationship between Toyotomi Hideyoshi, Akechi Mitsuhide and Nobunaga, three important figures in Japanese history?
- When can it be renovated in August 2022? The best decorated auspicious day in August 2022 is the zodiac.
- Yanji tourism policy